9

Location of the openings is the same as in the previ-

ous case - that is, within 12" of the top, and within 12"

of the bottom of the enclosure. If horizontal ducts are

used, the area must be doubled and the duct area

shall not be less than the area of the openings they

connect, and in no case shall the smallest dimension

be less than 3".

Venting Connections

These boilers have built-in drafthoods. Vent piping the

same size or larger than the drafthood outlet is recom-

mended; however, when the total vent height

(drafthood outlet to vent terminal) is at least ten (10)

feet, the vent pipe size may be reduced by one size

only as specified in the latest edition of the National

Fuel Gas Code, ANSI Z223.1.

As much as possible, avoid long horizontal runs of

vent pipe and too many elbows. If installation requires

horizontal runs, the vent pipe must have a minimum of

1/4 inch per foot rise and should be supported at not

less than five foot intervals. Maximum vent connector

horizontal length shall be 1-1/2 feet (18 inches) for

each inch of connector diameter as shown in Table E.

Gas vents supported only by the flashing and extend-

ing above the roof more than five feet should be

securely guyed or braced to withstand snow and wind

loads. We recommend use of insulated vent pipe

spacer through the roofs and walls.

For protection against rain or blockage by snow, the

vent pipe must terminate with a listed vent cap which

complies with the local codes or, in the absence of

such codes, to the latest edition of the National Fuel

Gas Code, ANSI Z223.1.

The discharge opening must be a minimum of two (2)

feet vertically from the roof surface and at least two (2)

feet higher than any part of the building within ten (10)

feet. Vent stack shall be at least five (5) feet in vertical

height above the drafthood outlet.

The vent cap location shall have a minimum clearance

of four (4) feet horizontally from, and in no case above

or below, unless a 4-foot horizontal distance is main-

tained, from electric meters, gas meters, regulators

and relief equipment.

The weight of the vent stack or chimney must not rest

on the boiler's drafthood. Support must be provided in

compliance with applicable codes. The boiler top and

drafthood must be readily removable for maintenance

and inspection. Vent pipe should be adequately sup-

ported to maintain proper clearances from combustible

construction.

Type "B" double-wall (or equivalent) vent pipe is rec-

ommended. However, single-wall metal vent pipe may

be used as specified in the latest edition of the

National Flue Gas Code ANSI Z223.1.

Model No.

Vent

Connector

Diameter (in.)

Max.

Horizontal

Length (ft)

0042

4

6

0066, 0090

5

7.5

0135

6

9

0180

7

10.5

Table E: Maximum Horizontal Length of Vent Pipe

Lowest Discharge

Opening

Listed Cap

Listed Gas Vent

X

12

Roof Pitch is X/12

H - Minimum Height from

Roof to Lowest

Discharge Opening

Fig. 4: Minimum Height from Roof to Lowest Discharge

Opening

Refer to Table F for detailed information