11
CONTRACT
OR
3.
Remove the template.
4.
Cut two (2) pieces of S-Cleat 8" long and one (1) piece 10-1/2" long.
5.
Place the 8" long S-Cleats on the narrow sides of the opening in the
duct, with the slots protruding down and out. Place the 10-1/2" long
S-Cleat on the longer side, closest to the center of the duct, in the
same way as the shorter S-Cleats.
6.
Attach the L-shaped bracket with six (6) holes to the top/front of the
humidifier, so that the vertical wall is toward the reservoir.
7.
Adjust the water level. (See #8 in “How To Maintain a Skuttle Steam
Humidifier”, pg. 25.)
8.
Slide the flanges of the reservoir into the S-Cleats until the mounting
bracket comes in contact with the side of the duct.
9.
Secure the humidifier to the duct with the screws provided.