As in all food service equipment, the Henny Penny open fryer does
require care and proper maintenance. The table below provides a
summary of scheduled maintenance procedures to be performed by
the operator.
Procedure
Frequency
Filtering of shortening
Daily
(Section 3-11)
Changing the filter pad
Daily
(Section 3-13)
Lubricate filter pan o-rings
Every filter pad change
Lubricate EEE-141 oil reservoir
When reservoir is
o-rings
removed
Changing of oil
When oil smokes,
foams up violently, or
tastes bad
Cleaning the vat
Every change of oil
(Section 3-15)
Inspect filter pan o-rings
Quarterly
(Section 3-16)
Inspect EEE-141 reservoir
Quarterly
o-rings (Section 3-10)