Equipment Location

7

4.0

E

QUIPMENT

L

OCATION

1. Handle cabinet(s) in accordance with the safety precautions in this manual, especially in these

sections:

Battery Cabinet Precautionsinside front cover
Important Safety Instructions—page 1
2.0 - Unloading and Handling—page 5
5.0 - Battery Installation—page 8

Use a suitable material handling device to move cabinet to its final location. Exercise extreme

care because of the uneven weight distribution. Carefully lower the cabinet to the floor.

2. Verify that the UPS system is installed in a clean, cool and dry location.
3. Installation and serviceability will be easier if adequate access is provided on all sides of the

equipment, but only front access is required.
a. Verify that there is adequate clearance to open cabinet doors—4 ft. (1.2m) is recommended.

NEC requires sufficient clearance in front of the equipment to fully open all doors without

restriction. See drawings and local codes.

b. Verify that there is adequate area in front of circuit breakers to perform maintenance. Check

installation drawings for location of breakers. Check with local codes.

c. Verify that there is adequate clearance above all cabinets to allow exhaust air to flow without

restriction. The minimum clearance is 2 ft. (0.6m), unobstructed by conduit or any other

items. Liebert recommends against using top-feed air conditioning systems.

4. Align the UPS cabinet, battery cabinets (if used) and optional transformer and maintenance

bypass cabinets, as shown in the Outline Drawing (Figure 9) and your submittal package.

5. Connect the cabinets, internal cables and busbars, if applicable. Internal control connections

should be left disconnected for later installation by Liebert LGS Customer Engineers.