2. Installation

2.6

Connecting the EBM(s)

To install the optional EBM(s) for a UPS:

A small amount of arcing may occur when connecting an EBM to the UPS. This is normal
and will not harm personnel. Insert the EBM cable into the UPS battery connector quickly and
firmly.

1. Plug the EBM cable(s) into the battery connector(s) as shown in figure 7. Up to four EBMs may be

connected to the UPS.

2. Verify that the EBM connections are tight and that adequate bend radius and strain relief exist for

each cable.

3. When using external battery cabinets, the number of EBMs should be set throw the LCD panel in the

"Battery settings" section, see "Configuring battery settings" on page 20.

4. Continue to "Installation requirements" on page 8.

Figure 7. Connecting the EBMs.

2.7 Installation requirements

Required protective devices and cable cross-sections

1. Recommended upstream protection (see figure 8)

Table 1. Upstream circuit breaker rating

UPS power rating

Upstream circuit breaker

5000 VA / 6000 VA

D curve – 40 A

G

N

L

N

L

Figure 8. Upstream protection.

2 poles circuit breaker

To UPS input source