Testing the function

Installation Guide

SBUS-PowBal-IUS102810

25

7 Testing the function

Check if the SMA Power Balancer operates correctly:

1. Select the "PhaseGuard" setting of the

"PowerBalancer" parameter for all three inverters.

2. Check whether all inverters in the group are feeding

the grid normally.
☑ If the green LED lights up steadily or if the

following display message appears, proceed
with point 3.

or
☑ If all inverters in this group show the adjacent

display message: Check the installation of the
SMA Power Balancer and contact the SMA
Serviceline if necessary.

3. Switch off the line circuit breaker for one of the

three inverters.
☑ The inverter with a deactivated line circuit

breaker indicates a grid voltage showing
following display message ("Bfr" and "Srr" are
irrelevant).

☑ The remaining inverters then also disconnect

from the grid showing following display
message.

☑ Both inverters subsequently switch to

"Balanced" mode.

☑ If the inverters react as described above, the

functionality test has been completed successfully.
Otherwise, check the configuration.

4. If applicable, reset the "PowerBalancer" parameter

to the desired setting in all inverters.

5. Switch on the line circuit breaker again.
6. The functionality test has been completed.