2 commissioning – Watson-Marlow APEX10 User Manual
Page 26
COMMISSIONING
26
6.2
Commissioning
1.
Connect the pipework.
2.
Make sure that there are no obstructions such
as closed valves.
3.
Switch on the hose pump.
4.
Check the rotation of the rotor.
5.
Check the capacity of the hose pump. If the
capacity differs from your specification, follow
the instructions in chapter
10
or consult your
Bredel representative.
6.
If a frequency controller is present, check the
capacity range. In case of any deviations
consult the supplier’s documentation.
7.
Check the hose pump in accordance with points
2 to 4 of the maintenance table at §
8.2
.