Initial Start Up

1. Remove front and left side panels. Check machine

for any packing or wires rubbing moving parts.

Note location of control board in upper left corner

of the machine’s front.

2. Switch on the electrical power to the machine.

Observe that some of the control’s indicator lights

glow and its display shows O.

3. Wait 4 hours for the compressor’s crankcase

heater to warm up the oil in the compressor.

4. Open the water supply valve.

5. Turn the receiver’s outlet valve to the full open

position.

6. Push and release the ON button.

The indicator light will begin to blink F. The purge

valve will open and the water pump will start. The inlet

water valve will open to add water to the reservoir.

After a few seconds the purge valve will close and the

water pump will stop. Water will flow into the machine

until the reservoir is full. The hot gas valves and

harvest assist devices will activate and the liquid line

solenoid valve will open, then the compressor, remote

fan motor and water pump will start. The display will

show a continuous F. Five seconds later the hot gas

valves will close and the harvest assist devices will

return to their standby positions. Warm air will be

discharged from the condenser coil.

7. During the Freeze cycle move the curtain and

observe that the SW1 or SW2 light on the control

board blinks ON when the curtain moves away

from the evaporator and OFF when returned to its

normal position.

Note: Moving the curtain during the Freeze cycle has

no affect on unit operation.

8. Observe the Ready for Harvest indicator light. It

may blink early in the freeze cycle, that is normal.

The control will ignore that signal for the first 6

minutes of freeze.

9. When the ice has frozen enough, the Ready for

Harvest indicator light will be on steady. After it’s

been on steady for a few seconds Harvest will

begin.

10. The display shows an H.

The hot gas valves open and the harvest assist

mechanisms are activated. The purge valve opens to

drain some water, when it does the inlet water valve

opens to refill the reservoir. After a few seconds the

purge valve closes but the inlet water valve continues

to fill the reservoir. Harvest continues until the ice is

released as a unit from each evaporator and forces

each curtain to open.

11. When both curtains have opened and re-closed

the controller returns the unit to a freeze cycle.

12. Check the ice harvested for proper bridge

thickness. The ice bridge is factory set at 3/16

inch. If needed, adjust bridge thickness. Do NOT

make it too thin.

13. Determine the water purge setting from the table

on the next page. If desired, change the setting to

accommodate the local water conditions.

14. Return the panels to their normal positions and

secure them to the machine.

15. Instruct the user in the operation of the machine

and its maintenance requirements.

16. Fill out and mail the warranty registration form.

Typical Ice Making Cycle Times (minutes)
Listed times are for clean machines. Cycle times at

startup will be longer until the system stabilizes.

Model

70

o

F. cond air

/50

o

F. water

90

o

F. cond air

/70

o

F. water

C1448R

11

14-15

C1848R

9-10

11

C2148R

10

12

December 2011

This manual is related to the following products: