Shut down the system using the
heat pump manager.
■
Switch off the power supply of
the outdoor unit.
■
Remove the right side panel.
This is achieved by undoing
three screws on the panel and
then pulling off the panel in a
downwards direction.
■
Connect the SYSTEM MONI-
TOR using the supplied connec-
tor to the CMN socket on the
control board of the outdoor
unit.
■
From page 7 onwards, you can
find a precise description of the
associated normal value ranges
of the System Monitor.
■
In the event of a fault, you can
find a precise fault description
with cause and remedy under
the "Fault codes" section.
■
Switch the power supply of the
outdoor unit back on.
■
Place the system back into
service using the heat pump
manager.
■
DIP switch SW2 allows targeted
diagnostics to be performed
Decommissioning
Operation
■
Shut down the system using the
heat pump manager.
■
Switch off the power supply of
the outdoor unit.
■
Remove the supplied connec-
tor for the SYSTEM MONITOR
from the CMN socket on the
control board of the outdoor
unit.
■
Switch the power supply of the
outdoor unit back on.
■
Place the system back into
service using the heat pump
manager.