Commissioning

NOTICE!

Commissioning should only be performed by

specially trained personnel and documented

after the certificate has been issued. Observe

the operating manuals for the indoor unit and

outdoor unit when commissioning the entire

system.

NOTICE!

Observe the operating manuals for the indoor

unit and outdoor unit when commissioning the

entire system.

Function test of cooling operating mode

1.

Switch the power supply on.

2.

Use the remote control to switch on the unit

and select the cooling mode, maximum fan

speed and lowest target temperature.

3.

Measure and record all the required values in

the commissioning report and check the

safety functions.

4.

Check the unit control system using the fol-

lowing functions described in the "Operation"

chapter: "Timer", "Temperature setting", "Fan

speeds" and switching to recirculation or

dehumidification mode.

5.

Check the correct function of the condensate

drainage line by pouring distilled water into

the condensate tray. A bottle with a spout is

recommended for pouring the water into the

condensate tray.

Function test of heating operating mode

1.

Switch the power supply on.

2.

Use the remote control to switch on the unit

and select the heating mode, maximum fan

speed and highest target temperature.

3.

Measure and record all the required values in

the commissioning report and check the

safety functions.

4.

Check the unit control system using the func-

tions described in the "Operation" chapter

(timer, temperature setting, fan speeds).

Final tasks

n

Re-install all disassembled parts.

n

Familiarise the operator with the system.

NOTICE!

Check that the shut-off valves and valve caps

are tight after carrying out any work on the

cooling cycle. Use appropriate sealant prod-

ucts as necessary.