1-2 normal power-on procedures – OPTI-UPS DS200KC33II User Manual

Page 27

background image

5-1-2 Normal Power-on Procedures

When the initial power-on procedure is done and the UPS is turned on. Press Inverter ON button on the
HMI control panel and Yes button on the pop-up window to restart the UPS. It will be turned on after 3
minutes.

Fig. 5-1-1 UPS Power-on/off Workflow

*) for 10K~30KVA models, fuses must be installed before the initial power-on operation.

Initial Power-on Procedures

:

Switch on

Switch off

Switch on

Switch off

SPS

S1

Power-off Procedures

:

Inverter status button

becomes green after

about 50 seconds

Bypass (Reserve) status button

becomes green

Switch on

Switch on

Switch off

Switch off

Switch on

*

S3

Switch on

Switch off

S2

BAT

Switch off

Press Inverter ON

Press Yes

Press Inverter OFF

Press Yes