beautypg.com

4 operation, 1 displays, 2 zeroing the gauge – Nor-Cal CDG 025 OP Lit User Manual

Page 19: 4operation

background image

CDG025-OP-LIT (2010-1)

19

4

Operation

Put the gauge into operation. If you are using a Nor-Cal con-
troller, select the measurement range.

A warm-up time of at least 15 minutes should be allowed; for
exact pressure measurements a warm-up time of at least
2 hours is required.

4.1

Displays

RUN

ZERO

LED

State

Meaning

lit

Measurement mode

flashing

Other mode, error


4.2

Zeroing the Gauge

The gauge is factory calibrated while "standing upright"
(

→ "Calibration Test Report").

We recommend performing a zero adjustment, when the

gauge is operated for the first time.

Due to long time operation or contamination, a zero drift could
occur and zero adjustment may become necessary.

For adjusting the zero, operate the gauge under the same con-
stant ambient conditions and in the same mounting orientation
as normally.