10.5 Hydraulic Plumbing

From this point on in the installation the booms will be inoperative until the

hydraulics are fully installed.

1. After the valves are mounted on the sprayer, the hydraulic hoses and fittings can be

installed (plumbed).

2. Install tee fittings (HARDI01) on the “P”, “T” and “B” port fittings at the HARDI block.

3. Connect pressure and tank lines between the HARDI block and the NORAC block.

4. The wing tilt “raise” must be connected to the “B” ports of the NORAC block in parallel

with the existing HARDI valve block.

 Connect the “B” ports of the NORAC block to the wing raise lines by connecting

HARDI02 between the “B” ports and the tee fittings installed in the HARDI block.

5. The “A” ports on the NORAC block are plugged. The “lower” lines of the cylinders are to

remain attached to the HARDI sprayer valve block.