9 Software Setup

1. Start up the sprayer and test the sprayer’s functionality. The NORAC control panel does

not need to be powered on for the original boom function switches to operate. Unfold the
booms and raise/lower each boom and the main section.

Confirm that the cabling and hoses are agreeable to the entire range of motion.

2. If any functions do not work, review the hydraulic and electrical portions of this manual to

check for proper installation.

3. Unfold the booms and level to 90 cm (or 35 inch) nozzle height. At this point ensure the

sensors are reading from an adequate and uniform target, such as gravel, dirt or concrete.

4. Begin the Automatic System Setup procedure as described in the UC4.5 Sprayer Boom

Control Operator’s Manual (M01). Select the RA1 type.

5. When finished the panel should display the Main Operating Screen:

M 90 M

(example)

This is indicating the system is ready for the second stage of installation. This will require
the manual calibration of the slant valve.

6. Press

until the display shows "More?". Press

to confirm. Press

until the display

shows "Roll?". Press

to confirm. Press the

to access the next menu prompt or

press

to access the previous menu. (Figure 33)

Figure 33: Roll Channel Valve Settings