Buffer tank installation, Aerco buffer tank installation and maintenance – AERCO Buffer Tanks User Manual

Page 6

background image

VD2: 08/27/12 Page 6 of 14

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, New York 10913 • Phone: 800-526-0288

AERCO Buffer Tank Installation and Maintenance

Technical Instruction Document

TID-0006_0B

3. BUFFER TANK INSTALLATION

Consult your local building codes for water heater regulations and make sure that you acquire

any necessary permits.
NOTE FOR MASSACHUSETTS INSTALLATIONS: Storage tank installations within the

Commonwealth of Massachusetts must conform to 248 CMR 10.00.

Refer to the user manual for the water heater being used to ascertain any special requirements

for your installation and proceed as follows:

Installing the Buffer Tank

1. Clear the area around installation site of all flammable and combustible materials.
2. Switch off the boiler/water heater and allow the system to cool for four hours.
3. Isolate the electrical supply to the existing boiler/water heater by switching off the

electricity at the mains supply point.

4. Turn off the cold water supply to the existing heating system and any other heating

appliance.

5. Turn off the main gas supply valve downstream from the boiler/water heater.
6. If you are replacing an existing buffer tank, be sure to drain and disassemble it according

to the manufacturer’s instructions.

7. Install drain fittings at bottom connection before setting the tank permanently.
8. Place the new tank into position and line it up to be flush with existing plumbing

connections. Connect the buffer tank to the plumbing using appropriate techniques.

9. Ensure ground wires to the boiler/water heater are connected.
10. Turn on mains electric power and mains gas upstream from the boiler/water heater.
11. Turn on the cold water supply to the tank, followed by the main water supply to the

system. Allow the tank to fill with cold water. Open the bleeder valve on the top of the

tank to vent air from the tank so it fills completely.

12. After installation, fill the system and run at operating temperature for at least one day in

a closed loop mode, then drain system, and re-fill.

NOTE

The tank should be installed in such a manner that should the tank

or any connections leak, the resulting flow of water will not cause

damage.