beautypg.com

EFCO 8800 Installation Instructions User Manual

Page 9

background image

EFCO 2009

Page 9

Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

Section 3 - Static Starter Sill Preparation and Installation

LC23

Silicone Sealant

WC19

End Dam - Attach
with (1) M153

Figure 1

Projects will be produced by EFCO in one of three ways: 1) As a stock length product where all fabrication, assembly, and glazing will be performed by

the customer, or: 2) Prefabricated “knock down” where EFCO fabricates the materials, and the customer performs the assembly, and glazing, or:

3) EFCO will provide a completely fabricated, assembled and glazed product. The materials shown here in the installation instructions may be received

in the field with varying degrees of shop assembly, with some items shop installed, and other items to be field installed. Certain assembly and installation

procedures shown and described in this document may be performed in the shop or the field at the discretion of the assembler.

1. Preparation of the Static Starter Sill:

a. The static starter sill may have an end dam pre-attached and sealed at the jamb condition. Ensure that the end dam is properly applied and sealed

to the starter sill as described below. This is a critical seal and the joint must be carefully tooled to create a watertight seal. See Figures 1, 2, and 3.

b. The starter sill may have gaskets (WC19 and LC23) pre-applied. The LC23 is cut to the length of the starter sill while the WC19 will be

approximately 6” to 8” longer than the starter sill. Do not cut off excess WC19. The excess gasket will be slid into the adjacent starter sill during
installation.

c. Plug the end of the tubular section of the starter sill at the jambs and corner conditions by recessing backer rod at least 1/4” into the end of the tube.

Fill the voids in the tube and between the thermal struts with sealant and tool smooth. Intermediate splice locations incorporate an internal splice
sleeve and will be covered later in this section.

Clean all sealant contact surfaces using an approved solvent or cleaner of all oils and other contaminants. The sealant manufacturer’s
preparation and application instructions should be followed exactly. If sealant primer is required, apply it per the primer/sealant
manufacturer’s instructions.

Figure 2

Figure 3

M153

Tool sealant smooth
into joints.

Plug with backer rod and fill the voids in

the tube and between the thermal struts

with sealant and tool sealant smooth.

Ensure LC23 and WC16
butt into the end dam fully.

This manual is related to the following products: