Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

2. When

re-glazing an opening or openings at a captured unit, follow these instructions:

a. Using an approved solvent or cleaner, clean the glazing surfaces of all oils and other contaminants. The sealant manufacturer’s

preparation and application instructions should be followed exactly. Fresh sealant will adhere to cured sealant without primer. Primer may be
necessary if the sealant has been completely removed.

b. Replace WC18 preset spacer gasket with new gasket around the entire opening. Ensure the gaskets are firmly butted together in the corners.
c. Run a bead of sealant around the WC18 gasket as shown below. The joint must be filled with sealant in excess so that it will fill all voids between the

glazing and the WC18 gasket when the glazing is put in place. Tool the sealant into a beveled shape as shown below prior to setting the glazing.
Ensure no voids or air bubbles are present in the sealant. The glazing must be set within 10 minutes or before the sealant begins to skin over.

Section 14 - Deglaze / Re-glaze Procedures - Captured System

Figure 135

Figure 136

Note:
Only silicone sealants which have been
developed and tested specifically for
structural glazing applications should
be used for re-glazing purposes.

Apply new WC18

spacer gaskets.

WC18 Gasket

High modulus
silicone sealant.

WC18 Gasket

Apply a small backer rod at void

High modulus

silicone sealant.

Apply sealant

around the opening

and tool as shown.

Apply sealant

around the opening

and tool as shown.