Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

Section 12 - Applying Critical Seals

Apply sealant on top

of the primary seal

gasket and raceway.

Create a bed of

sealant to lay the

gutter splice into.

Figure 121

Figure 122

1. Once the two units are installed, a splice is required at the gutter at the top of the units. Clean the gutter sill sealant contact surfaces using an approved

solvent or cleaner of all oils and other contaminants where the gutter splice will be applied. The sealant manufacturer’s preparation and
application instructions should be followed exactly. If sealant primer is required, apply it per the primer/sealant manufacturer’s instructions.

2. Apply a bed of sealant on the gutter that will cover the area where the gutter splice (HC08 or HC09) will be applied. When creating the bed of sealant, apply

a generous amount of sealant directly on top of the primary seal location as shown in Figure 121.

3. The sealant must go from the front of the gutter up the engagement leg to the WC19 gasket track. See Figure 123 of the following page. The sealant bed

must be wide enough to cover the entire area of the gutter splice (HC08 or HC09). See Figure 122.

HC08 or HC09 Silicone
Splice Sleeve

Ensure WC19 gasket
has been butt sealed
together.