Problems - Solutions
Problems
Solutions
The unit does not switch on
Check
- unit/power supply connections
- power cable fuses
Calibration test
Check
- calibration factor
- shutters are closed
Repeat the stationary test.
Shutters open to maximum then to minimum
Check
- Tractor forward speed coefficient
- spreading width
(24.00 - note the position of the decimal point)
The unit switches on but the actuators do not move
Check
- Fuses
The area meter reading is incorrect
Check
- connection / machine
- working width
- forward speed
Flow rate
Check
- programmed flow rate
- fertiliser coefficient
- PTO speed = 540 rpm
- spreading width
- tractor’s forward speed
- shutter opening/closing performance
- actuator travel
- tramlining
The forward speed rate is incorrect
Check
- connection on unit
- sensor magnet clearance
- magnet rotation
- sensor wire continuity
(resistance 100 ± 10)
- 100-m coefficient
The tonnage counter reading is incorrect
Check
- connection / machine
- working width
- forward speed
- fertiliser coefficient
- shutter opening/closing