Installation and Commissioning Plan

Criterion

TM

Series 60 5

A2.0 INSTALLATION PROCEDURE

The system will be installed by an FSE. Depending on the system configuration,
the following activities will be performed:

Item Description

Performed

On Site

A2.1

Verify that all components purchased are present

according to the purchase contract and packing list.

A2.2

Remove packaging on the load unit (for example

mounting clamps and oilpaper).



A2.3 Install

the

cover

boards



A2.4

Attach all required cables between controller and load

unit.

-

Transducers.

-

Computer.

A2.5

Attach all hoses between load unit and Integrated

Operations Platform.



A2.6

Fill hydraulic oil to the reservoir.



A2.7

Install purchased grips and fixtures as required

(including any auxiliary power supplies for grips.)

A2.8

Install purchased environmental simulation products.

(For example, safety enclosure, steps and furnace)