CHECKLIST—INSTALLATION

LOAD CALCULATION

____________

Heating Load (Btuh)

____________

Cooling Load (Btuh)

____________

Furnace Model Selection

VENT PIPING

Termination Location

________

Roof or Sidewall

________

Vent Pipe Length

________

Vent Pipe Elbow Quantity

________

Pipe Diameter Determined from
Sizing Table

________

Pipe Sloped To Furnace

Pipe Insulation

________

Over Ceilings

________

Low-Ambient Exposed Pipes

Condensate Drain

________

Unit Level or Pitched Forward

________

Internal Tubing Connections Free
of Kinks and Traps

________

External Drain Connection Leak
Tight and Sloped

________

Condensate Trap Primed before
Start-Up

________

Heat Tape Installed if Required

CHECKLIST—START-UP

________

Gas Input Rate (Set Within 2
percent of
Rating Plate)

________

Temperature Rise Adjusted

Thermostat Anticipator

________

Anticipator Setting Adjusted or

________

Cycle Rate (3 Cycles per Hr) Se-
lected

Safety Controls Check Operation

________

Primary Limit

________

Pressure Switch

—39—