Operation – Battery Replacement
990-1599B Smart-UPS® VT 10-30 kVA, 208/220 V and XR Battery Enclosure Operation Manual
31
Install the Battery Modules in the lowest available bay (4 across in 20.59inch/523mm UPS
versions, 2 across in 13.85inch/352mm UPS versions).
Position the Battery Unit to slide in between the grooves and push completely into the UPS to
ensure connection.
Note
If a problem is reported, ensure that the modules in question are correctly installed. If the
problem persists, refer to the Troubleshooting section of this guide.
Note
Allow for a 24-hour recharging period of the batteries after system start-up / battery
replacement for battery monitoring data to become fully reliable.
Model:
Serial:
BATTERY UNIT
Model:
Serial:
BATTERY UNIT