Clock set-up – American Power Conversion XR User Manual
Page 20
![background image](/manuals/42308/20/background.png)
Operation – Navigation
12
Smart-UPS® VT 10-30 kVA, 208/220 V and XR Battery Enclosure Operation Manual 990-1599B
Load and batteries.
Load: Percentage of the load in relation to the total UPS capacity.
Bat Voltage: shows either the positive or negative half of the battery voltage (the lower value of the
two will appear).
Bat Cap: Percentage charge on the batteries in relation to the total battery capacity.
Runtime: The predicted runtime at the current load.
Batteries.
Bat AmpHr: Battery capacity, including both external and internal batteries.
UPS Temp: The highest external battery temperature.
Alarm thresholds.
Load: An alarm will be set when the load is above the threshold level.
Runtime: An alarm will be set when the runtime is below the threshold level.
Clock set-up
From the Setup screen on the Main Menu, you can change the date and the clock setting. From the
Settings screen, select Clock, and press ENTER. A date and a time line will appear.
Time.
The clock function is used to time-stamp events in the event log. To avoid inaccuracies, change the
clock-setting at e.g. daylight-saving time.
Date
• To change the date, press ENTER (the day field will become active). Press the UP/DOWN
arrow to select the desired date.
• To change the month and the year, follow the same procedures.
• Press ENTER to confirm the new settings, or ESC to cancel.
Time
• To change the time, press ENTER (the hour field will become active). Press the UP/DOWN
arrow to select the desired time.
• Follow the same procedure to change the minute and the second fields.
• Press ENTER to save, or ESC to cancel.