Functional test, Preventative maintenance, Installation – Outback Power Systems GS4048A Installation Manual User Manual
Page 40
Installation
38
Functional Test
Once the mounting, wiring, and other installation steps are completed, proceed to the Radian Series
Inverter/Charger Operator’s Manual. The Operator’s Manual has steps for system commissioning. These
include powering up and performing a functional test on the inverter system, as well as powering
down and adding new devices to an existing system.
Refer to the MATE3 System Display and Controller Owner’s Manual (or the appropriate system display
manual) for programming instructions and menus.
Preventative Maintenance
The Radian inverter requires almost no regular maintenance. However, OutBack recommends the
following items on a periodic basis:
Check all electrical connections periodically for tightness using the torque values from pages 19 through 22.
Check the fan screens on each module and clear them of any debris.