7.

Install the PCI-X/PCI Express I/O expansion board.

8.

Install any expansion boards ("

Installing a non-hot-plug expansion board

" on page

57

).

9.

Install the access panel.

10.

Slide the processor memory drawer back into the server.

11.

Slide the server back into the rack.

12.

Power up the server (on page

25

).

HP NC524SFP Dual Port 10GbE Module option

IMPORTANT:

The NC524SFP Dual Port 10GbE Module option is compatible only with the

NC375i SPI board.

When installed on the SPI board, the HP NC524SFP Dual Port 10GbE Module provides two 10G NIC
connectors for server I/O. When the HP NC524SFP module is installed, 1G NIC connectors 1 and 2 on the

rear panel are unavailable.

IMPORTANT:

When both an HP NC524SFP module and an optional HP NC522SFP Dual Port

10GbE Server Adapter are installed in the server, only expansion slot 1 has Wake On LAN

capability.

To install the component:

1.

Power down the server (on page

25

).

2.

Disconnect the network cables.

3.

Extend the server from the rack (on page

25

).

4.

Remove the access panel (on page

26

).

5.

Remove the SPI board (on page

29

).