Hardware options installation 48
6.
Identify the expansion slot compatible with the new option, and then remove the cover opposite that
slot.
7.
Install the expansion board.
8.
Install the PCI riser cage (on page
IMPORTANT:
The server does not power up if the PCI riser cage is not seated properly.
9.
Connect all necessary internal and external cables to the expansion board. For more information on
these cabling requirements, see the documentation that ships with the option.
10.
Install the access panel (on page
11.
Do one of the following:
o
Slide the server into the rack.
o
Install the server into the rack ("
Installing the server into the rack
" on page
12.
Connect each power cord to the server.
13.
Connect each power cord to the power source.
14.
Dedicated iLO management port option
To install the component:
1.
Power down the server (on page
2.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
3.
Do one of the following: