Installation Guide APC BC300 Series 60kW 208/480V UPS

990-1400A

Installation

Greenly punch

Equipment suitable for lifting heavy UPS off the ground

3.2.1 Conduit Connection Kit Contents

For Pedestals:

23 pedestals

4 M8 x 100 mm bolts

4 M8 lock washers

4 M8 flat washers

4 M8 nuts

For Conduit Box:

1 Conduit Box

1 Conduit Box Cover

11 M5 x 12 mm T20 Torx screws

11 M5 lock washers

11 M5 flat washers


For Base Covers:

2 Side Base Covers

2 Front/Rear Base Covers

Hook and loop fasteners

3.2.2 Installing Pedestals

1) Remove brackets mounted to the UPS feet during shipping

2) Lift the UPS off the floor and place the pedestals under UPS feet where the holes of

pedestals and holes in UPS feet are aligned

3) With caution lower the UPS feet into pedestal

4) Fasten but DO NOT TIGHTEN bolts, washers and nuts on the four corner feet of UPS

5) Move the UPS to the installation site

6) Tighten the bolts

3.2.3 Installing Conduit Box and Base Covers

1) Punch conduit holes in the back of the conduit box

CAUTION!

Heavy Equipment. Use caution and appropriate equipment to safely lift the UPS several inches
above the floor when installing pedestals.

NOTICE!

Place flat washer under the bolt head and the lock washer under the nut.