5 COMMISSIONING
5.11
System Flushing: This pump incorporates push-in connectors
and plastic components that must not come into contact with
solder flux, acid-based descalents or aggressive cleaning agents.
The pipework system should be flushed out prior to the pump
being connected to ensure any contaminants/chemical residues
and foreign bodies are removed from elsewhere in the system.
5.12
Water Supply: Always ensure that water storage capacity is adequate to meet
the demand. Ensure the pump chamber is full of water before starting the pump.
Failure to do this could result in seal damage. To ensure dry running does not
occur the pump must be primed as described in priming section below.
Do not run pump dry.
5.13
Priming:
Never operate pump with inlet and/or outlet isolating valves in the
closed position. Damage will occur!
The pump must be primed (filled with water) before starting.
Turn on the service valves (1), and vent/prime pump head.
(a) Loosen priming plug (2) and allow an even flow of water this may take a
few
seconds.
(b) Re-seal draining plug, nipping tight. The pump is now ready to start.
Fig. 14
1
1
2 Priming
Plug