King Electrical Floor Heating Mat Installation Manual

13

STEP 4R: Electrical rough-in (For Remodel)

Cut Hole for remodel J-box

Install remodel J-box

4.1R Determine the proper location and height
(typically 60”) for the
junction box. The cold lead and the floor sensor

lead wires should be in the same stud cavity as the
electrical junction box.

4.2R Install a remodel type electrical junction box

for the thermostat and run the supply power into the

box.

Install Nail Plate

4.3R Remove base moldings as needed where the

4.5R Install a nail plate to protect the wires.

cable routing holes need to be drilled.

4.4R Chisel out a 1-1/2” by 1-1/2” channel into

the sill plate 1-1/2” deep. If installing a floor sensor, chisel a
second relief 4” away in the same stud cavity.