4.3.1 Installing the Split-Core Current Sensor Assembly

Each phase being monitored will require one two-piece current sensor assembly.

Therefore, a three-phase meter will require three (3) assemblies. Open the two-piece

current sensor assembly by releasing the nylon clamp using a flat head screwdriver.

Fig. 3. Split-Core Current Sensor Assembly

1. Reassemble the current sensor assembly around the conductor(s) to be moni-

tored. Ensure the current sensor halves marked “Load” are both facing the load

side of the conductor. The colored arrow will be on the source side of the con-

ductor being monitored and MUST be pointed in a clockwise direction around

the conductor being monitored. Tighten the nylon clamp to complete the assem-

bly.

Fig. 4. Arrow On The Current Sensor Assembly

IMPORTANT:

When looking from the source side of the conductor(s) being monitored, you

should see the arrow on the current sensor assembly. The arrow should be

pointing in a clockwise direction around the conductor(s) being monitored. If

the arrow is not positioned on the source side, inaccurate readings will result.

4.3.2 Installing the Solid-Core Current Sensor Assembly

The optional solid-core current sensors can be installed in the same applications as

the standard split-core units, however, the conductors that they are monitoring must

first be disconnected.

NOTE: Under no circumstances is this operation to take place without shutting off the

power to the conductor(s) being monitored.

M33213

LOAD

SOURCE