Section 2 – wiring – Controlled Products Systems Group 9100-080 User Manual
Page 27
SECTION 2 – WIRING
Before attempting to connect any wiring to the operator, be sure that the circuit breaker in the
electrical panel is in the OFF position. Permanent wiring must be installed to the operator as required
by local electrical codes. It is recommended that such work be performed by a licensed electrical
contractor.
Since building codes vary from city to city, we highly recommend that you check with your
local building department prior to installing any permanent wiring to be sure that all wiring to
the operator (both high and low voltage) complies with local code requirements.
THIS GATE OPERATOR MUST BE PROPERLY GROUNDED!!
PRIMARY
OPERATOR
SECONDARY
OPERATOR
Low Voltage Control Devices
Loop Lead-In Wires
High Voltage Power
SLIDE GATE CONDUIT REQUIREMENTS
(Typical)
Figure 23
• The conduit requirements shown in figure 23 are for a typical slide gate operator installation
(the secondary operator is shown for those applications where a secondary operator may be
used). The conduit requirements for your application may vary from this depending on your
specific needs.
• Use only sweeps for conduit bends. Do not use 90° connectors as this will make wire pulls
very difficult and can cause damage to wire insulation.
• We suggest that minimum ¾-inch conduit be used.
• Be sure that all conduits are installed in accordance with local codes.
9100-065-D-5-07
Page
27