beautypg.com

Controlled Products Systems Group 106753 User Manual

Page 7

background image

7

FAAC Model 770 24V Underground Swing Gate Operator

b) For Existing Gates with Adjustable Hinges:

• Remove the bottom hinge.
• Slacken the top hinge.
• Swing the leaf around the axis of the top hinge (Fig. 4).

c) Installing a New Gate:

Fit just the top hinge. If possible use an adjustable hinge.
1. Dig a hole for the foundation box as shown in Fig. 5.

Fig. 4

S

6⅛

~12⅜

6⅛

~17⅜

Fig. 5

Fig. 6b

~17⅜

~12⅜

90°

Fig. 7

Ø 1⅜

2. Place the foundation box in the hole, refer to the dimen-

sions provided in Figs. 6a and 6b.

The center of the pivot on the foundation box must be perfectly

aligned with the leaf’s axis of swing (Figs 6a and 6b).
3. Lay down a 2" Liquid Tight Conduit, it must be long enough

to reach from the box to the control unit (Fig. 7). Lay a sec-

ond conduit to drain rain water from the box to the nearest

drain (also Fig. 7).

4. Fix the box in place with a casting of concrete.

Fig. 6a

* Measurements

in Inches

* Measurements in Inches

* Measurements in Inches

* Measurements

in Inches

12⅛

17

6⅛

Fig. 3

* Measurements in Inches

3.2 INSTALLING THE LOAD BEARING BOX

a) For Existing Gates with Fixed Hinges:

• Remove the gate.

• Remove the bottom hinge.

If the gate cannot be removed, place blocks under its bottom

edge to support it.

Depending on the nature of the ground, it may be necessary to

cast a bed of quick-setting concrete at the bottom of the hole to

avoid subsidence in future.