Commissioning and decommissioning

6.2 Decommissioning/

storing

Stop the machine

a) Switch the machine off.

b) If available close the cut off device in the suction

and pressure pipe.

c) Disconnect the machine from the electricity

source.

d) Depressurise the machine: Open the pipes

slowly

The pressure reduces slowly.

e) Remove the pipes and hoses.

f) Seal the connections for suction and discharge

nozzles with adhesive foil.

g) Discharge cooling water (Fig. 3/D

1

).

see also Section 3.2.1, Page 11

6.3 Re-commissioning

a) Check the condition of the machine (cleanliness,

cabling etc.).

For installation see Section 5 Page 18

For commissioning see Section 6.1 Page 23