5.1

Preparing for installation

Check the following points:

Machine freely accessible from all sides

Do not close ventilation grids and holes

Suffi cient room for installing and removing pipes
and for maintenance work, particularly for install-
ing and dismantling the machine

No external vibration effects

Do not suck any hot exhaust air from other ma-
chines into the cooling system.

The oil fi lling point (Fig. 2/H, H

1

), oil sight glass (Fig. 2/I, I

1

) and oil outlets (Fig. 2/K, K

1

), cooling

water inlet (Fig. 3/C) and cooling water outlet (Fig. 3/D) must be easily accessible.
The cooling air inlets (Fig. 3/E) and cooling air outlets (Fig. 3/F) must be at least 30 cm away from
adjacent walls. Cooling air coming out must not be sucked in again.

5.2 Installation

NOTICE

The machine may only be operated when it is
set up horizontally.

Material damage resulting from the machine
tipping over and falling.

When installed at more than 1000 m above sea
level a reduction in power is noticeable. In this
case we would ask you to contact us.

Contamination in the intake air
To protect the machine the operator should install
appropriate fi lters on the suction side.

Check for oil leakage
Risk of falling in oil spills!

Ensure that the foundation complies with the follow-
ing conditions:

Level and straight

The bearing surface must be designed to be
able to take the weight of the machine.

It is possible to install the machine on a fi rm base without anchoring. When installing on a sub-