Foundation requirements, Level the base on a concrete foundation, Grout the baseplate – Xylem 10 001 247 R2 TechnoForce Package System User Manual
Page 15

Guideline
Explanation/comment
Make sure that the space around the pump package is
sufficient.
This facilitates ventilation, inspection, maintenance, and
service.
If you require lifting equipment such as a hoist or tackle,
make sure that there is enough space above the pump
package.
This makes it easier to properly use the lifting equipment
and safely remove and relocate the components to a safe
location.
Protect the unit from weather and water damage due to
rain, flooding, and freezing temperatures.
This is applicable if nothing else is specified.
Do not install and operate the equipment in closed
systems unless the system is constructed with properly-
sized safety and control devices.
Acceptable devices:
• Pressure relief valves
• Compression tanks
• Pressure controls
• Temperature controls
• Flow controls
If the system does not include these devices, consult the
engineer or architect in charge before you operate the
pump.
Take into consideration the occurrence of abnormal noise
and vibration.
The best pump location for noise and vibration
absorption is on a concrete floor with subsoil underneath.
Foundation requirements
Requirements
• The foundation must be able to absorb any type of vibration and form a permanent,
rigid support for the unit.
• Provide a flat, substantial concrete foundation in order to prevent strain and distortion
when you tighten the foundation bolts.
• Sleeve-type and J-type foundation bolts are most commonly used. Both designs allow
movement for the final bolt adjustment.
Level the base on a concrete foundation
1. Place the pump package on its concrete foundation.
2. Place 1.00 in./(25.40 mm) thick steel shims or wedges on both sides of each anchor
bolt in order to support the pump package.
Make sure you also place the shims or wedges midway between the bolts.
This also provides a means of leveling the base.
Grout the baseplate
Required equipment:
• Cleaners: Do not use an oil-based cleaner because the grout will not bond to it. See
the instructions provided by the grout manufacturer.
• Grout: Non-shrink grout is required.
1. Clean all the areas of the baseplate that will come into contact with the grout.
2. Build a dam around the foundation.
3. Thoroughly wet the foundation that will come into contact with the grout.
4. Pour grout into the baseplate up to top of the base rails.
To hold wedges or shims in place, allow the grout to flow around them.
Follow grout manufacturer's instructions for removing air pockets from grout during
pour.
Installation
TechnoForce Package System Mechanical Installation, Operation, and Maintenance Manual