Installation, Reference manuals, Field connections – Xylem 10 001 247 R2 TechnoForce Package System User Manual
Page 14: Earth (ground) connections, Pump package location guidelines

Installation
Reference manuals
Additional installation information
For information on installing controllers, use the following IOM:
• Technologic = S14367 — constant speed systems
• TechnoForce Pump Controller = 10–001–265 — variable speed systems
Field connections
Diagrams
Actual equipment manufacturers/models installed are system specific. Refer to specific
manufacturer Installation, Operation, and Maintenance manuals for details unique to each
component. The pump instruction manual is supplied with the system.
Review the wiring diagrams and dimensional drawings before you install and operate the
unit.
Electrical precautions
WARNING:
Electrical shock hazard. The electrical supply must match the control panel nameplate
specification. Incorrect voltage can cause a fire, which damages the electrical components
and voids the warranty. Failure to follow these instructions could result in serious personal
injury or death, or property damage.
NOTICE:
Electrical connections must be made by certified electricians in compliance with all
international, national, state, and local rules.
Earth (ground) connections
WARNING:
Electrical shock hazard. Conduit grounds are not adequate. You must attach a separate
earth (ground) wire to the earth (ground) lug provided in the enclosure in order to avoid
potential safety hazards. Failure to follow these instructions can result in serious personal
injury, death, or property damage.
A grounding terminal is provided for a dedicated earth (ground) wire connection. You
must follow all provisions of the National Electrical Code and local codes.
Pump package location guidelines
WARNING:
Assembled units and their components are heavy. Failure to properly lift and support this
equipment can result in serious physical injury and/or equipment damage. Lift equipment
only at the specifically identified lifting points. Lifting devices such as eyebolts, slings, and
spreaders must be rated, selected, and used for the entire load being lifted.
Installation
12
TechnoForce Package System Mechanical Installation, Operation, and Maintenance Manual