Trim Installation

1.Utilizing 3/4” copper pipe, make connections between spout, valves and water supply.

See Figure 3. Warning: To prevent severe damage to valve body, any solder/braze

process must be performed a min. of 4" from ports.

2.Place the O-RING (9) and ESCUTCHEON (11) onto STEM (12). Secure HANDLE (8) into

place by first engaging the STEM (12) and then threading MOUNTING NUT (7) onto car-

tridge. Any adjustments for rotational alignment must be made to the valve body, not to

the cartridge. Repeat on other side. See Figure 4. (Cartridge Bonnet factory torque is 14-

16 ft-lbs.)

3.Turn on water supply, and flush both valves until water is clear.

4.Check for leaks and make any final adjustments required.

Figure 3

Inlet for

hot

water

supply

Inlet for

cold water

supply

Figure 4

8

11

12

9

NWP-1-656

EN-2108

REV -