ISSUED: 08-10-09 SHEET #: 139-9011-2 04-29-10

Attaching Solid•Point

Column Mounts to Extension Columns

Insert four M10 x 15 mm penta-pin screws (

L) into threaded holes on the sides of ceiling arm box (H) as shown in

figure 3.1. Leave approximately 1/4" of exposed thread as shown in detail 1.
Slide ceiling arm box (

H) onto end of extension column (A) followed by extension column fiber washer (K) and

retaining collar (

E) as shown in figure 3.2. Tighten retaining collar and align slot of extension column (A) with hole

of retaining collar (

E).

3

Back View

fig. 3.1

DETAIL 1

fig. 3.2

fig. 3.3

DETAIL 2

Slot

Small hole

Insert and tighten one M5 x 10 mm penta-pin screw (

J) through the hole of the retaining collar (E) and slot of ex-

tension column (

A) as shown in figure 3.3.

Insert one M5 x 10 mm penta-pin screw (

J) through the tab on the back of ceiling arm box (H) as shown in detail 2.

Use the M5 penta-pin tool (

N) to tighten screws. Repeat step three to attach second ceiling arm box (H).

NOTE: Both ceiling arm boxes (H) must be at same height to attach adapter plate (Q) properly.

3-2

L

H

A

E

K

J

J

1/4"