10. Service
PNEG-1707 TM-Series Tower Dryer
51
Pre-season Service Check List
___ Lubricate blower motor bearings, if needed.
___ Clean burner ports.
___ Inspect flame rod and spark ignitor.
___ Inspect divider hopper between heat and cooling section. Clean if necessary.
___ Inspect bindicator grain level switches.
___ Check gas pressure gauges.
___ Clean control and power panels, tighten loose connections, and check for leaks.
___ Inspect metering systems. Clean accumulated stalks and old grain.
___ Start-up dryer and check operating controls.
___ Other: Itemize ___________________________________________________________
End of Season Shut Down Procedure
___ Start unload and empty all grain from dryers.
___ Clean out grain cushion (on plenum roof under fill spout). Clean plenum roof.
___ Clean off grain exchangers.
___ Clean out divider hopper, between heating and cooling section.
___ Clean inside cooling sheets and cooling floor.
___ Remove all grain and trash from unload section of dryer.
___ Open emergency grain discharge doors.
___ Open drain valve in gas train.
___ Cover burner with a tarp or plastic sheeting.