11. Pre-Season Checks
28
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow
Drying Chamber
Inspect each dump hopper for obstructions.
Make sure that the gap between the discharge flow plates and the floor sheets is a minimum of 38 mm.
Rotary Switches
Check all rotary switches are spinning freely.
Linear Actuator
Turn the Dump switch “manual open”.
Check the stroke on the actuator is 300 mm to 350 mm. Adjust if necessary.
Make sure that all pulleys and cables move freely.
With the actuator extended, view each dump chute to make sure they are completely open.
The dump chutes should hinge smoothly.
Turn Dump switch to “AUTO” position and press the Stop switch. The chutes should raise.
Power Start Button
Ensure there is grain in the wet supply tank.
Push the dryer Start button. The screen should no longer flash “STOPPED”.
Fuel Check
Check for leaks as described previously.
Fan
Check fan rotates freely and in the correct direction. (See fan direction decal
.) If required
reverse the fan by swapping over phases L1 and L3.
Make sure the fan runs smoothly with no vibration.
Aeration Fan
Check fan rotates freely and in the correct direction. (See fan direction decal
.) If required
reverse the fan by swapping over phases L1 and L3.
Make sure the fan runs smoothly with no vibration.