9. Sidewall Assembly

PNEG-603 4" Commercial Hopper Tank

37

Sidewall Erection Instructions (Continued)

NOTE: The rope caulking is installed before each sheet is assembled. Apply rope caulking between the

last vertical row of bolts and edge of outside sheet. There is sufficient caulking for all vertical seams
on storage and drying bins. Wipe sheet clean where caulking is to be applied.

Figure 9B Tighten Bolts in Order