5 Connecting to power supply
VEGAFLEX 81 • Modbus and Levelmaster protocol
42283-EN-130314
+
+
power supply
MODBUS
D0
D1
IS GND
USB
1
2
1
3
4
5
2
off on
( )
(
)
(-)
(-)
Fig. 13: Connection compartment
1 USB connection
2 Slide switch for integrated termination resistor (120 Ω)
Terminal
Function
Polarity
1
Voltage supply
+
2
Voltage supply
-
3
Modbus-Signal D0
+
4
Modbus-Signal D1
-
5
Function ground with installa-
tion according to CSA
5.4 Switch-on phase
After connecting the instrument to power supply or after a voltage
recurrence, the instrument carries out a self-check for approx. 30 s:
•
Internal check of the electronics
•
Indication of the instrument type, hardware and software version,
measurement loop name on the display or PC
•
Indication of the status message "F 105 Determine measured
value" on the display or PC
•
The output signal jumps to the set error current
As soon as a plausible measured value is found, the corresponding
current is outputted to the signal cable. The value corresponds to the
actual level as well as the settings already carried out, e.g. factory
setting.
Connection compartment