Liebert UPSTATION GXT 2U User Manual
Page 15

11
7. Insert the UPS, with inner members attached from Step 3, into the
slide assemblies. You may need to depress the locking mechanisms
on the inner and outer members of the slide assemblies to allow the
slides to retract. The UPS should move smoothly forward and back-
ward on the slide assemblies. If not, recheck alignment.
8. To orient the display for horizon-
tal viewing, remove the front
plastic bezel by pulling forward
evenly on both sides. The unit
has two front panel overlays.
Remove the outer overlay (used
for tower installation). This
reveals a horizontally oriented
front panel overlay for rack
mounting. Snap the front bezel
back into place.
9. Once the UPS is installed in the
rack, the load may be con-
nected. Ensure the load equip-
ment is turned off; plug all loads
into the output receptacles on
the rear of the UPS.
10. Plug the UPS into a dedicated
wall receptacle properly pro-
tected by a circuit breaker or
fuse in accordance with national
and local electrical codes. Use a 15 amp rated device for the 700,
1000, or 1500 VA units, 20 amp for the 2000 VA, and 30 amp for the
3000 VA. The wall receptacle must be grounded.
11. Turn ON the UPS by pressing the ON button; then turn on the con-
nected load equipment. The UPS is now providing conditioned power
to your equipment.
!
CAUTION
Reduce the risk of tipping the rack enclosure by
placing the UPS in the lowest possible rack position.
+
–
UPStation GXT
AC INPUT
BATTERY
UPS ON
BYPASS
+
–
UPStation GXT
AC INPUT
BATTERY
UPS ON
BYPASS
Vertical
overlay
for
tower
UPS
Horizontal overlay
for rack UPS