For more information visit: www.Eaton.com

IB01602011E

Instructional Booklet

Page 16

Effective: March 2007

Fixed and Drawout Magnum Transfer Switches

3.8 Standards

Eaton transfer switch equipment is listed for application by UL and

CSA. In addition, Eaton ATSs are listed in File E38116 by

UL, Inc., under Standard UL 1008. This standard covers require-

ments for ATSs intended for use in ordinary locations to provide

for lighting and power as follows:

a. In emergency systems, in accordance with articles 517 and

700 in the National Electrical Code (NEC), American National

Standards Institute/National Fire Protection Association

(ANSI/NFPA) 70 and the NFPA No. 76A and/or

b. In stand-by systems, in accordance with article 702 of the

NEC and/or

c. In legally required stand-by systems in accordance with article

701 of the NEC.

Eaton ATSs are available to meet NFPA 110 for emergency and

stand-by power systems, and NFPA 99 for health care facilities

when ordered with the appropriate options.
Since Eaton ATSs utilize specially designed switches and/or

switching devices as the main power switching contacts, these

devices must also be listed under the additional UL Standard

1066. UL utilizes two basic types of listing programs: a) Label

Service and b) Re-examination. UL1066 employs a label service

listing program which requires an extensive follow-up testing pro-

gram for listed devices. Standard UL1008 for ATSs lists devices

under the re-examination program which only requires a continual

physical re-examination of the components used in the product to

insure consistency with the originally submitted device. Follow-up

testing IS NOT required by UL1008.
Representative production samples of switches and switching

devices used in Eaton ATSs are subjected to a complete test pro-

gram identical to the originally submitted devices on an ongoing

periodic basis per UL1066. The frequency of such a re-submittal

can be as often as every quarter for a low ampere device.

Section 4: Installation and Wiring

4.1 General

Eaton transfer switches are factory wired and tested. Installation

requires solidly mounting the enclosed unit and connecting the

power cables and auxiliary pilot circuits. Physical mounting proce-

dures and power cable connections are covered in this section.

All other required wiring or electrical connection references are

covered in a separate Customer Wiring Diagram packaged with

the transfer switch.
Locate the wiring booklet, review it, and keep it readily available

for reference purposes during installation and testing. Once a

transfer switch is properly installed and wired, it should be

mechanically and electrically checked for proper installation and

operation. The procedures for these initial mechanical and electri-

cal checks are outlined in Section 8.1 of this instruction manual.

4.2 Mounting Location

Choose a location that offers a flat, rigid mounting surface capa-

ble of supporting the weight of the enclosed transfer switch

equipment. Avoid locations that are moist, hot, or dusty. How-

ever, Eaton offers enclosure designs that can be used in special

environments. If there are any doubts as to the suitability of the

location, discuss it with your Eaton representative.
Check to make certain that there are no pipes, wires, or other haz-

ards in the immediate area that could create a problem. The pan-

els provide ample room for rear cable entry from top, bottom, and

sides. At no time should cable be routed to retard the action of

relays or cover the logic in a way that restricts adjustments.

Maintain proper electrical clearances between live metal parts and

grounded metal.
For installation and maintenance purposes, the Source 1 and

Source 2 power sources must have an overcurrent protective

device upstream of the transfer switch, unless overcurrent protec-

tion is integral to the switch.
The dimensions of the transfer switch are an important consider-

ation in determining proper location selection.

WARNING

BE CERTAIN THAT THE SOLID STEEL POWER PANEL SHIELDS ARE

PROPERLY INSTALLED BEFORE THE TRANSFER SWITCH EQUIP-

MENT IS PUT INTO SERVICE. THE SHIELD PROVIDES PROTECTION

FROM DANGEROUS VOLTAGES AT THE LINE AND LOAD TERMI-

NALS WHEN THE EQUIPMENT IS IN OPERATION. FAILURE TO DO

SO COULD RESULT IN PERSONAL INJURY OR DEATH.