Verifying the Installation


1/1531-HSD 101 41 Uen A 2004-01-30

13

This method is similar to activating real subscribers. In order to use this
method the following preconditions have to be fulfilled:

The PEM installation has succeeded

The PEM configuration of the network has been done

The servers in the network are running

All registration has been transferred to the PEM

The Service Configuration Manager is used for this task.
Alternatively the Bulk Configuration Manager can be used instead of the
Service Configuration Manager and may simplify the task of configuring an
end-user with a service for each line; please see the Bulk Configuration
User’s Guide
for further details.

Please refer to Local Craft Tool User’s Guide and the PEM User’s Guide for
detailed information of how to use them.

Table 3

Verification with the ECN320 Local Craft Tool

Verification Activity

Comments

Perform continuity check on each line from
the Exchange MDF to the Line MDF

Best to perform after rewiring and

before installing nodes

Verify that the green LED is lit on the IP
DSLAMs

Green – The IP DSLAM has booted
and received an IP address and SW

Verify (if possible) that the ECN320 switch
port where the IP DSLAMs are connected,
indicates active Ethernet connection

Active Ethernet connection is
verified

Recommended to perform check on each
ADSL line

Testing the IP DSLAM functionality

Recommended to perform continuity check
on each POTS or ISDN line

Test that the new installation has
not affected the old services

Start the Status Manager and use the Flash
LEDs button to verify the MDF position of the
IP DSLAMs (verification of the registration)

Test of the registration process