Verifying the Installation

10

1/1531-HSD 101 41 Uen A 2004-01-30

5

Verifying the Installation

The purpose of the verification is to ensure the following:

No errors in the rewiring of the subscriber lines

The old services (POTS or ISDN) function

The physical installation of the EDA Access Domain nodes was done

correctly

The power and Ethernet connections function

It is possible to make an ADSL connection to a CPE modem

The registration in PEM has been done correctly

The following methods can be used for verification, each implying a
different level of verification and effort:

1. Verification without connection to PEM or any management system

2. Verification using the Local Craft Tool (LCT).

3. Verification

using

PEM.

5.1

Verification without Connection to PEM

It is not possible to activate the IP DSLAM by this method. It is the least
time consuming method but also gives the least assurance. This method
involves the following:

Table 1

Verification without Connection to Management System

Verification Activity

Comments

Perform continuity check on each line from
the Exchange MDF to the Line MDF

Best to perform after rewiring and

before installing nodes

Verify (if possible) that the ECN320 switch
port where the IP DSLAMs are connected,
indicates active Ethernet connection

Active Ethernet connection is
verified

Recommended to perform continuity check
on each POTS or ISDN line

Test that the new installation has
not affected the old services