8 checklist for completed installation, Checklist for completed installation, Table 21 – Emerson Precision Cooling For Business-Critical Continuity Figure i User Manual
Page 28
Installation
24
2.8
Checklist for Completed Installation
___ 1. All items unpacked and checked.
___ 2. Proper clearances for service access maintained around equipment.
___ 3. Equipment is level and mounting fasteners are tight.
___ 4. Piping completed to refrigerant loop.
___ 5. All piping connections are tight.
___ 6. Piping routed to prevent chafing and rub-through.
___ 7. Piping has been evacuated and refrigerant charge added (if required).
___ 8. Line voltage to power wiring matches equipment nameplate.
___ 9. Power wiring connections completed, including earth ground.
___ 10. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 11. Control wiring connections completed.
___ 12. All wiring connections are tight.
___ 13. Foreign materials have been removed from area: in and around all equipment installed
(shipping materials, construction materials, tools, etc.).
___ 14. Fans and blowers rotate freely and in the proper direction.
___ 15. Blank startup sheet has been sent with the evaporator unit and is ready to be completed by
the installer.
Table 21
Electrical data - Quiet-Line models (95°F/35°C) 50Hz
Model #
Nominal
Capacity
Tons
* Electrical
Characteristic
Input Voltage-Phase
220-1
200/230-3
380/415-3
13
1
FLA
—
—
—
19
1.5
FLA
—
—
—
26
2
FLA
12.3
—
4.8
36
3
FLA
18.0
—
6.9
41
3.5
FLA
—
17.3
8.4
66
5
FLA
—
22.5
12.4
95
8
FLA
—
—
—
* FLA = Full Load Amps