Recommissioning the Inverter

Requirements:

☐ The inverter must be correctly mounted.
☐ The circuit breaker must be correctly rated.
☐ All cables must be correctly connected.

Procedure:

1. Attach the connection cap to the inverter using

the three screws and a Torx screwdriver (TX20)
(torque: 3.5 Nm).

1

2

3

2. Tighten the swivel nuts of the AC cable gland and network connection hand-tight.
3. Set the DC load-break switch of the inverter to position 1.
4. Switch on the circuit breaker.

☑ The green LED flashes slowly on and off or glows permanently. Feed-in operation begins.

✖ Green LED is flashing?

The DC input voltage is still too low.

• Once the DC input voltage is sufficiently high, feed-in operation begins.

✖ The red LED is glowing?

There is probably an error.

• Call up the inverter user interface (see Section 3 "Calling Up the Inverter User

Interface via Direct Connection", page 8).

• Call up the menu Events and identify the error via the event ID.
Rectify the error (see Section 4 "Event Messages", page 10).

5. If required, configure the inverter via the user interface.