SMA SB 1.5-1VL-40 Service Manual User Manual

Page 13

background image

Event number

Message, cause and corrective measures

801

Waiting for grid voltage > Grid failure > Check AC circuit breaker
The AC cable is not correctly connected or the country data set is not correctly
configured.
Corrective measures:

• Make sure that the circuit breaker is switched on.
• Ensure that the AC cable is not damaged and that it is connected

correctly.

• Ensure that the country data set has been configured correctly.
• Check whether the grid voltage at the connection point of the inverter is

permanently in the permissible range.
If the grid voltage is outside the permissible range due to local grid
conditions, contact the grid operator. The grid operator must agree with
an adjustment of the voltage at the feed-in point or with a change of the
monitored operating limits.
If the grid voltage is permanently within the permissible range and this
message is still displayed, contact the Service (see Section 11 "Contact",
page 33).
.

901

PE conn. missing > Check connection
The grounding conductor is not correctly connected.
Corrective measures:

• Ensure that PE is correctly connected (see operating manual of the

inverter).

1001

L/N swapped > Check connection
The connection of L and N is swapped.
Corrective measures:

• Ensure that L and N are correctly connected (see operating manual of

the inverter).

1101

Installation fault > Check connection
A second line conductor is connected to N.
Corrective measures:

• Connect the neutral conductor to N.

4 Event Messages

SMA Solar Technology AG

Service Manual for Installers

13

SB15-25-SG-en-10