beautypg.com

7 back boring (cycle 204, din/iso: g204), Cycle run, Back boring (cycle 204, din/iso: g204) – HEIDENHAIN TNC 640 (34059x-02) Cycle programming User Manual

Page 83

background image

BACK BORING (Cycle 204, DIN/ISO: G204)

3.7

3

TNC 640 | User's Manual Cycle Programming | 5/2013

83

3.7

BACK BORING (Cycle 204, DIN/ISO:
G204)

Cycle run

This cycle allows holes to be bored from the underside of the
workpiece.

1 The TNC positions the tool in the tool axis at rapid traverse

FMAX to set-up clearance above the workpiece surface.

2 The TNC then orients the spindle to the 0° position with an

oriented spindle stop and displaces the tool by the off-center
distance.

3 The tool is then plunged into the already bored hole at the

feed rate for pre-positioning until the tooth has reached set-up
clearance on the underside of the workpiece.

4 The TNC then centers the tool again over the bore hole,

switches on the spindle and the coolant and moves at the feed
rate for boring to the depth of bore.

5 If a dwell time is entered, the tool will pause at the top of the

bore hole and will then be retracted from the hole again. The
TNC carries out another oriented spindle stop and the tool is
once again displaced by the off-center distance.

6 The tool then retracts to set-up clearance at the feed rate for

pre-positioning, and from there—if programmed—to the 2nd
set-up clearance at

FMAX.